Lindegas PrimA4a steel CO2 pipeline in Haarlemmermeer

Client
Linde Gas Benelux
Contractor
VSH
Implementation period
August 2020 - February 2021
Products
5.000 meter DN500 en DN300 Steel / PP-coating (DIN 30678)
Certification
EN 10204 / 3.2 + NEN 3650

Lindegas PrimA4a

OCAP started with the installation of a base pipeline for delivering CO2 to the horticulture area PrimA4a in Haarlemmermeer.

Because OCAP delivered reused CO2, originating by Shell Pernis and bio-ethanol producer Alco, this instalment has been a huge step forward in sustaining the horticulture in Greenport Aalsmeer.

CCI Leidingsystemen delivered the complete pipelines: both pipes and induction curves, but also the flanges and fittings. All according to NEN 3650 and inclusive 3.2 certificates according to EN 10204.

All pipe parts have been coated and blasted internally.

CCI has built up the needed know-how for these kinds of projects in the last 40 years. If you want advise or information about these kinds of projects (or other projects, like hydrogen)